Kootenai County is laying the groundwork for a major taxiway rebuild at the Coeur d'Alene Airport next spring, while also updating the airport's master plan and testing new drone-detection technology.
At a county meeting on October 7, airport staff reviewed a taxiway reconstruction project targeted for May 2027. The project is part of a longer-running effort: the county already applied earlier this year for Federal Aviation Administration grants covering the taxiway work, with county commissioners approving the application at their February 10 meeting. Airport staff put the total project cost at $3,162,303, with an anticipated 95 percent reimbursement from the FAA and a county cash match of roughly $79,058.
The Idaho Transportation Department's draft 2027-2033 transportation improvement program corroborates the plan, listing a "Rehabilitate Taxiway A" project at the Coeur d'Alene Airport with $2 million in construction costs — $1.8 million federal and a $200,000 local match — under project number 23468. The same document lists follow-on work including runway decoupling and a taxilane extension for future fiscal years.
Beyond the pavement, county officials said the airport is updating its master plan and will solicit public input as part of the process. The airport is also testing a new drone-detection system and preparing for an upcoming FAA inspection.
The county-owned airport in Hayden, also known as Pappy Boyington Field, is the region's primary general-aviation hub, serving business and recreational flyers across North Idaho and the Spokane area. Past county actions at the airport have included taxiway lighting improvements funded largely through FAA grants and a snow-removal equipment upgrade — both signs of the steady federal-local investment the facility requires to keep operating safely.
No construction timeline beyond the May 2027 target has been announced. The master-plan update will be the public's main chance to weigh in on the airport's long-term direction, and county officials are expected to release details on how residents can participate in the coming months.